Assisted Rio Tinto Alcan Weipa (RTAW) with the preparation & finalisation of the Draft Network Technical Rules (NTR), specific clause extracted from Chapter 5 Schedule 5.1 & 5.2 of the NER. Performed generator modeling, develop technical design compliance report for presentation to RTAW. Technical review of balance of plant concept design with plant improvements including connection strategies recommended to RTAW. Generator & control system compliance testing & develop technical design validation report for RTAW to sign-off & grant Commercial Operations. Project value, ~$5M